Paper presented at the Biogas Training Programme Conducted at CARD,
Alam Village, Myitkyina.
Metta Development Foundation
Biogas Construction Process
Govinda Prasad Devkota
P.O. Box 20506 Kathmandu, Napal
govindadevkota@yahoo.com.
Introduction:
The success of the plant depends upon the construction. In this paper the construction process of the fixed dome design biogas plant developed by Gobar Gas Company in Nepal is presented.
Measurement of different size of biogas plants:
Part of the plant | Plants size in Cubic meter | |||||
4 | 6 | 8 | 10 | 15 | 20 | |
A | 140 | 150 | 174 | 180 | 248 | 264 |
B | 120 | 120 | 130 | 125 | 125 | 176 |
C | 135 | 151 | 170 | 183 | 205 | 233 |
D | 50 | 60 | 65 | 68 | 84 | 86 |
E | 154 | 155 | 172 | 168 | 180 | 203 |
F | 102 | 122 | 135 | 154 | 175 | 199 |
G | 185 | 211 | 221 | 240 | 261 | 288 |
H | 86 | 92 | 105 | 94 | 115 | 115 |
I | 112 | 116 | 127 | 124 | 132 | 137 |
J | 151 | 110 | 175 | 171 | 193 | 203 |
Note: All the measurements are given in Centimeter.